S
Steve Haines
Hello,
I'm trying to Print Grid in Project Center with projects that are
linked togather. I'm unable to get the views that I want. I have a
master schedule and I have inserted sub projects into this master
schedule and now i would like to view the task under those
subprojects for a specific view. I need to be able to view the
subprojects and am unable to do so. Is there a way to print this
master schedule with all of it's sub projects even though they are
linked without breaking the link? I'm also only looking for specific
information within these sub projects and only want to print/export
those items. I'm using MS Project Server 2003 (11.2.2005.1801.15) SP2
Thanks,
Steve
I'm trying to Print Grid in Project Center with projects that are
linked togather. I'm unable to get the views that I want. I have a
master schedule and I have inserted sub projects into this master
schedule and now i would like to view the task under those
subprojects for a specific view. I need to be able to view the
subprojects and am unable to do so. Is there a way to print this
master schedule with all of it's sub projects even though they are
linked without breaking the link? I'm also only looking for specific
information within these sub projects and only want to print/export
those items. I'm using MS Project Server 2003 (11.2.2005.1801.15) SP2
Thanks,
Steve