Hi Julia,
My replies are embedded. I hope this helps. Let us know how you get
along.
Julie
Julia said:
Great thanks for your reply.
You're welcome and thanks for the feedback.
The left most column appears to be the 'Information' column and
there are no ID no.'s, just a blue 'Information' heading. Is this
what you are refering to?
No, usually the left most field showing in the table is the ID field.
It is light gray in color because it is usually locked. (It looks
like the row numbers you may see in Excel.) The column to the right
of the ID column that you refer to is the Indicator column.
I've inserted Levelling Delay field then Levelled 1 Resource and
nothing has populated the field, as mentioned. I'm not actually
sure what the levelling did. Is there a way to see what Project has
done compared to what was there before? The only thing I notice is
that the Task Summary is not red anymore.
The Resource Leveling command will only delay tasks where a resource
is overallocated. If you had no overallocated resources, it is
possible that the command didn't do anything. To view tasks that are
delayed, take a look at the Leveling Gantt. The green bars indicate
where the task was scheduled prior to leveling, the blue bars show
where the task is now. If you chose to allow project to level
individual assignments on a task, the task may not have been leveled
but the assignment for a resource may have delay.
Regarding Assignment Start, please can you let me know which field I
can enter the Assignment Start Date as it doesn't appear in Column
Definition?
You will insert the Start field into the table. In the Resource
Usage View, the Start field added to the table (left side) shows both
the date the resource starts working in the project (in the row with
the resource's name). The assignment row (indented underneath the
resource's name) shows the assignment start date.
Generally, there is no need to enter the assignment start dates.
They are calculated by project based upon the start date of the task
and the resource's working calendar. Perhaps if you described
further why you want to enter assignment start dates I can assist
further.
Kind regards.
"JulieS" <passport6847 at maine dot rr dot com> wrote in message
Hi Julia,
My answers are embedded within.
I hope this helps. Let us know how you get along.
Julie
Can you please let me know why you have advised ID again to see
Assignment ID's?
The ID column which shows by default in the Resource Usage view as
the left most column (locked) is the Resource ID. You said earlier
that you wanted to see the IDs of the assignments as well. But
inserting the ID column into the Usage table you will be able to
see the assignment IDs as well.
I have modified Resource Usage and added columns except that I am
unable to insert a 'Delay' column when attempting to Insert Column
and then creating a Text field allocating 'Delay' to it. When
attempting this, the column was empty.
Try inserting the Assignment Delay field and the Leveling Delay
field. The Assignment delay field is the difference between the
Task Start and the Assignment Start. You may delay a Resource's
assignment to a task in a situation where you may wish one resource
to start after another Resource beings their work on a task. The
Leveling Delay field is usually populated if you delay assignments
through the Resource Leveling command. Once you have inserted the
two fields, you can view Help information by hovering your mouse
over the column heading and choosing the Help on [Field Name]
hyperlink.
Regarding modification of the To Do Report, I wasn't quite sure
but are you > suggesting to use the Resource Usage (or Task Usage
view) and add the appropriate columns for the better results and
layout?
Yes. The built in reports (such as the To-Do Report) are hard to
modify as you wanted. My suggestion about modification of the
Resource Usage or Task Usage view was in response to your comment
about liking the information available in the Resource Form.
"JulieS" <passport6847 at maine dot rr dot com> wrote in message
Hi Julia,
My suggestion is to create a new table or modify the existing
table applied to the Resource Usage view. Add the additional
columns that you like: ID, Project, ID (again to see Assignment
IDs), Name, Work, Leveling Delay, Delay, Start, and Finish.
You can then collapse the assignments for the other resources
under their name. If you wish, you could then insert page breaks
to force each resource to their own page.
Modification of the To Do Report is a bit tougher, but again, you
may get close to what you want by using the Task Usage view,
adding the additional fields: Project, Leveling Delay, Delay and
then use the Using Resource... filter to display only information
for specific resources. Then print that view with only the left
side visible.
I hope this helps. Let us know how you get along.
Julie
Hi
The Resource Name Form has exactly the information I would like
for each Resource. The heading with the information I need are
Project, ID, Task Name, Work, Leveling Delay, Delay, Start,
Finish. I want to print this individually in this format for
each Resource.
I just checked Resource Usage View - this is ok but I want to
see just one individual Resource's Start and Finish dates in a
similar format to Resource Name Form.
I also checked To Do Report - This is better but the ID column
is 'messy', as it shows "Week of 02 January" and on the next
line "ID 2" and so on... Can I amend the layout to fit more
neater to the page?
Thank you
"JulieS" <passport6847 at maine dot rr dot com> wrote in message
Hi Julia,
The Resource Name Form is used as the lower part of a
combination view and is not printable. If you wish to get a
list of assignments for a resource you could print the To Do
list Report or print a filtered view from the Resource Usage
View. Perhaps if you give us some additional information about
what you mean by a "print out of the schedule", we can better
advise.
I hope this helps. Let us know how you get along.
Julie
Hi
When I apply 'Resource Name Form' view, I am unable to print
indiviual Resource schedules.
Do you know how I can get a print out of the schedule?
Thanks in advance.