R
Roger Becker
Good Morning All,
I've been pouring over this issue for days and haven't come to any
logical reason for why it's happening. I am hoping someone here may have had
the same issue or knows if I've just made a simple error.
Heres the situation - I have 5 test cells lets call them T1 thru T5 and
when in use two workers man each test. For any given test, the resource
column shows T1, Test[2]. I have 6 workers to man test cells, so of the 5 I
can run 3 at any given time. Here is my issue later in the year when I reach
my highest possible test load project is producing leveling delays for the
test resource I don't understand.
For instance only 4 of the test resource are being used ie two tests
are being conducted, however there are other tests available to be started in
other test cells, but project won't start them. The test cells are available.
It seems that project does not recgonize that there are 6 test resouces
available.
I have noticed this is more prevalent as the jobs become lower in
priority, however there is not a large difference in priority between the
jobs in question. Are there different priority groups I may not be aware of?
I know I'm grasping at straws, but I've checked all the calendars, working
hours, links, constraints and still I have available work, available manpower
& available cells but I have leveling delays.
Can anyone shed some light on this and help me keep my sanity?
Thank you!
Roger
I've been pouring over this issue for days and haven't come to any
logical reason for why it's happening. I am hoping someone here may have had
the same issue or knows if I've just made a simple error.
Heres the situation - I have 5 test cells lets call them T1 thru T5 and
when in use two workers man each test. For any given test, the resource
column shows T1, Test[2]. I have 6 workers to man test cells, so of the 5 I
can run 3 at any given time. Here is my issue later in the year when I reach
my highest possible test load project is producing leveling delays for the
test resource I don't understand.
For instance only 4 of the test resource are being used ie two tests
are being conducted, however there are other tests available to be started in
other test cells, but project won't start them. The test cells are available.
It seems that project does not recgonize that there are 6 test resouces
available.
I have noticed this is more prevalent as the jobs become lower in
priority, however there is not a large difference in priority between the
jobs in question. Are there different priority groups I may not be aware of?
I know I'm grasping at straws, but I've checked all the calendars, working
hours, links, constraints and still I have available work, available manpower
& available cells but I have leveling delays.
Can anyone shed some light on this and help me keep my sanity?
Thank you!
Roger