priority

A

andre

Why can't you change the priority when in resource usage view. I want to
assign a resource and see evertying he/she is assigned to and use that to set
his/her priority

Thanks,,]

Andre
 
A

andre

I think I answered my own question. I found 1 way at least. I split the
window and put the tracking gaant at the top and the resource usage at the
botton.
 
J

JulieS

Hello Andre,

As you discovered, priority is a task variable, not an assignment
variable. You can add the priority field to any *task* view (such as
Task Usage). You'll discover that when you have multiple resources
assigned to a task that the assignments get the same priority and cannot
be changed.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


andre said:
I think I answered my own question. I found 1 way at least. I split the
window and put the tracking gaant at the top and the resource usage at
the
botton.

andre said:
Why can't you change the priority when in resource usage view. I want
to
assign a resource and see evertying he/she is assigned to and use
that to set
his/her priority

Thanks,,]

Andre
 