i got two questions:
a)
When something is going for "2 weeks" the graphics shows two weeks. But
these go through the whole weekend, even when on saturday/sunday nobody
should work! May I disable this so that graphics are only shown as from
monday to friday for two (or more weeks)?
b)
I entered the eMail-address of a resource. Is it in any way possible to
instruct PROJECT that when in case of X (X = definded by me) an eMail is sent
to this address?
Thanx for quick help!
Niels Brabandt
i got two questions:
a)
When something is going for "2 weeks" the graphics shows two weeks. But
these go through the whole weekend, even when on saturday/sunday nobody
should work! May I disable this so that graphics are only shown as from
monday to friday for two (or more weeks)?
b)
I entered the eMail-address of a resource. Is it in any way possible to
instruct PROJECT that when in case of X (X = definded by me) an eMail is sent
to this address?
Thanx for quick help!
Niels Brabandt