I'm using Project 2000 and have a split view with the Gantt Chart up top and
Task Usage on the bottom.
I've right clicked the space on the lower right window (the one with the
yellow coloured calendar) and added Work and Actual Work. The two rows are
then displayed for each resource.
That is all fine and works ok, my question is why can't I view the Details
column in this same lower right window that heads up each row and tells me
which is Work and which is Actual Work? I've seen it on other versions of
Project that are installed in my workplace and I've also tried right click,
Detail Styles.../Usage Properties/ and have set Display details header column
to Yes. It still doesn't appear.
Has anyone else had a similar experience and been able to tweak anything?
Task Usage on the bottom.
I've right clicked the space on the lower right window (the one with the
yellow coloured calendar) and added Work and Actual Work. The two rows are
then displayed for each resource.
That is all fine and works ok, my question is why can't I view the Details
column in this same lower right window that heads up each row and tells me
which is Work and which is Actual Work? I've seen it on other versions of
Project that are installed in my workplace and I've also tried right click,
Detail Styles.../Usage Properties/ and have set Display details header column
to Yes. It still doesn't appear.
Has anyone else had a similar experience and been able to tweak anything?