Marina Garrison
I am using MS Project Web Access and am unable to get the
tasks to accept daily actuals (currently only actuals for
period and remaining work).
I have set both the Admin / Cust Web Access to:
- Hours of work done per day or per week: Resources
report the hours worked on each task during each time
period;
- Allow project managers to change the default method for
reporting progress if a different method is appropriate
for a specific project;
- Resources should report their hours worked every day.
In the project under Tools / Customize / Published fields
the "Hours of work done per time period" (the MS Project
Server Admin has set default period to days)
How do I get it to accept daily actuals?
Marina
tasks to accept daily actuals (currently only actuals for
period and remaining work).
I have set both the Admin / Cust Web Access to:
- Hours of work done per day or per week: Resources
report the hours worked on each task during each time
period;
- Allow project managers to change the default method for
reporting progress if a different method is appropriate
for a specific project;
- Resources should report their hours worked every day.
In the project under Tools / Customize / Published fields
the "Hours of work done per time period" (the MS Project
Server Admin has set default period to days)
How do I get it to accept daily actuals?
Marina