T
tshad
This is driving me crazy.
I have a small project that have only 9 tasks
A few are parallel tasks with some Lag in start times and the start dates
seem to be fine.
Where I have a problem is with a task (#7) which is only 16 days long (3
weeks) but the end date is about 13 weeks after the start date?????
I originally had only one resource (100%) and thought maybe that was the
problem so I created 3 resource (staff<1,2,3>) but that didn't change
anything. The Gantt looks like:
1 Prepare 10 days 7/7 7/18 Staff1
2 First 5 days 7/21 7/25 "1,3" Staff1
3 Preparation 5 days 7/7 7/11 Staff1
4 Schedule 10 days 7/28 8/8 2 Staff1
5 Second 2 days 8/15 8/18 2FS+14 days Staff2
6 Study 20 days 8/26 9/22 2FS+21 days Staff3
7 Study 16 days 9/23 12/25 "6,5,4" Staff1 <----
8 Study 5 days 12/26 1/1 7 Staff1
9 Study 1 day 1/2 1/2 8 Staff1
I spent an hour trying to figure out what the problem was. Then to see - I
changed the duration to 1 day and it went 9/23-9/23. Then I put 16 days
back in and it was not 9/23 - 10/14 (which is correct).
What?????
What was the problem?
Thanks,
Tom
I have a small project that have only 9 tasks
A few are parallel tasks with some Lag in start times and the start dates
seem to be fine.
Where I have a problem is with a task (#7) which is only 16 days long (3
weeks) but the end date is about 13 weeks after the start date?????
I originally had only one resource (100%) and thought maybe that was the
problem so I created 3 resource (staff<1,2,3>) but that didn't change
anything. The Gantt looks like:
1 Prepare 10 days 7/7 7/18 Staff1
2 First 5 days 7/21 7/25 "1,3" Staff1
3 Preparation 5 days 7/7 7/11 Staff1
4 Schedule 10 days 7/28 8/8 2 Staff1
5 Second 2 days 8/15 8/18 2FS+14 days Staff2
6 Study 20 days 8/26 9/22 2FS+21 days Staff3
7 Study 16 days 9/23 12/25 "6,5,4" Staff1 <----
8 Study 5 days 12/26 1/1 7 Staff1
9 Study 1 day 1/2 1/2 8 Staff1
I spent an hour trying to figure out what the problem was. Then to see - I
changed the duration to 1 day and it went 9/23-9/23. Then I put 16 days
back in and it was not 9/23 - 10/14 (which is correct).
What?????
What was the problem?
Thanks,
Tom