D
Dee
I have resources that I need to set for particular availability on a project,
but don't want them to show as having any other remaining availability other
than for that project. I'm using the Resource Availability box under Resource
Information, and setting the start/end dates and available units. But the
units are not setting; it either wants 1 or 0. It was working last week! I
could set availability to be any percentage I wanted for a set range of
dates. Not sure what's happened, but this is very important so that these
resources are not counted as overall available when I run monthly reports.
But I still want to show who's working on a project. Can anyone tell me
what's happened here and how to be able to reset specific availability?
Thanks!
but don't want them to show as having any other remaining availability other
than for that project. I'm using the Resource Availability box under Resource
Information, and setting the start/end dates and available units. But the
units are not setting; it either wants 1 or 0. It was working last week! I
could set availability to be any percentage I wanted for a set range of
dates. Not sure what's happened, but this is very important so that these
resources are not counted as overall available when I run monthly reports.
But I still want to show who's working on a project. Can anyone tell me
what's happened here and how to be able to reset specific availability?
Thanks!