M
Marilyn
I have a task that starts 7/2/07 - 10/31/07 with a duration of 88d. I have
to resources assign to that task Lori and 30% and FEM at 60%. When I look at
the Resource Usage and I look at the task assign to Lori it only has 35.2h
for the month of July and it does not expand to October which is when the
task is supposed to be finished. I don’t think this is calculating
accurately.
Can someone help?
Thanks,
to resources assign to that task Lori and 30% and FEM at 60%. When I look at
the Resource Usage and I look at the task assign to Lori it only has 35.2h
for the month of July and it does not expand to October which is when the
task is supposed to be finished. I don’t think this is calculating
accurately.
Can someone help?
Thanks,