B
basstwo
Here is the data I have to start with: 'Bob' needs to make 30
'boards'. He does so and it takes 6 hours. I now want to make a task
that encapsulates this transaction. So I make a task "Build Boards".
Duration = 0.75 days (6 hours). I make a material resource 'boards'
and set the units to '5 boards/hour' (30 boards/6 hours). This equates
out to a 'work' value of '30 boards'. I can now increase the 30 to 40
and the duration with adjust to 1 day. But I have two thin gs I cannot
seem to get to work.
First thing: If I add 'Bob' as a work resource (added under 'boards'
in the task form) it will show that he must work 6 hours to complete
the boards. But if I adjust the number of boards needed from 30 to 40
it now stops adjusting the duration (it stays at 0.75 days) and it
won't increase the hours 'Bob' must work from 6 to 8.
Second thing: The big project is to make 30 'boxes'. Each box
requires a 'board' along with a bunch of other tasks. So, I can
complete my schedule for a run of 30 'boxes'. But if I need to make
another run but of 40 'boxes' then do I have to go to EASH task and
change the quantities ('work' value of 30 boards for the "Build Boards"
task, various other numbers for other tasks depending on how many are
used in a 'box') everywhere!?!
I read on a post about a guy who uses Excel to figure out quantities
and then OLEs them into Project. That sounds dangerous...so I make the
'work' value link to the value in Excel?
Thank you for your time! Sorry this is so long!
'boards'. He does so and it takes 6 hours. I now want to make a task
that encapsulates this transaction. So I make a task "Build Boards".
Duration = 0.75 days (6 hours). I make a material resource 'boards'
and set the units to '5 boards/hour' (30 boards/6 hours). This equates
out to a 'work' value of '30 boards'. I can now increase the 30 to 40
and the duration with adjust to 1 day. But I have two thin gs I cannot
seem to get to work.
First thing: If I add 'Bob' as a work resource (added under 'boards'
in the task form) it will show that he must work 6 hours to complete
the boards. But if I adjust the number of boards needed from 30 to 40
it now stops adjusting the duration (it stays at 0.75 days) and it
won't increase the hours 'Bob' must work from 6 to 8.
Second thing: The big project is to make 30 'boxes'. Each box
requires a 'board' along with a bunch of other tasks. So, I can
complete my schedule for a run of 30 'boxes'. But if I need to make
another run but of 40 'boxes' then do I have to go to EASH task and
change the quantities ('work' value of 30 boards for the "Build Boards"
task, various other numbers for other tasks depending on how many are
used in a 'box') everywhere!?!
I read on a post about a guy who uses Excel to figure out quantities
and then OLEs them into Project. That sounds dangerous...so I make the
'work' value link to the value in Excel?
Thank you for your time! Sorry this is so long!