Progress line doesn't highlight ahead activities [by right outde.

D

Double O

Progress line does not make a right-ward dent to show an activity is ahead.
It only show a left-ward dent to show an activity is behind schedule. How do
I fix this?
 
J

JulieS

Hi Double O,

Try displaying the Progress line in relation to the baseline plan. (On
Dates and Intervals tab.)

That should show the right-ward dent when you are ahead of the baseline
schedule.

I hope this helps. Let us know how you get along.

Julie
 