Progress lines

J

j.vente

Hi,

Is it possible to create a progress line which shows progress for
detail tasks, but doesn't show progress for summary tasks?

Thanks,

Jan Vente
 
D

davegb

Hi,

Is it possible to create a progress line which shows progress for
detail tasks, but doesn't show progress for summary tasks?

Thanks,

Jan Vente

Progress on Summary lines is based on progress on working tasks, so it
shouldn't affect progress lines.

Hope this helps in your world.
 
J

j.vente

davegb schreef:

Progress on Summary lines is based on progress on working tasks, so it
shouldn't affect progress lines.

Hope this helps in your world.

Hi Dave,

But it does affect. When in insert a progress line on status date, the
progressline indicates the progress on the tasks and the summary tasks.
My customer want a straight line with the summary tasks.

(Sorry for my poor English. I hope you understand.)

Jan
 
D

davegb

davegb schreef:



Hi Dave,

But it does affect. When in insert a progress line on status date, the
progressline indicates the progress on the tasks and the summary tasks.
My customer want a straight line with the summary tasks.

(Sorry for my poor English. I hope you understand.)

Jan

I don't have Project where I am, so I can't actually try stuff before I
suggest it. What if you filter the view and hide the summary lines?
 