Ginger said:
Hi John,
Can you use the formula below with an example. I have the same question and
I think that would help me to understand.
Thanks, ginger
ginger,
First of all, WoW!! You're send key must have gotten stuck big time.
Really, we will see the message on the first posting - really.
I'm not sure how an example illustrates the concept so let me throw a
few more words at it and then give an example.
A summary line is not a task and it is unfortunate that Project calls it
a task. The intent of a summary line is to, well, summarize the data
contained in the subtasks under it. With regard to progress, the summary
line needs to somehow combine the effects of progress on each subtask.
There are probably various formulas that could be used but the one that
makes the most sense is to use a weighted average. In the case of
summary line % complete, Project adds up the Actual Durations of all
subtasks and divides by the sum of all subtask durations and coverts to
a percentage.
Here is the example. A plan has a summary line with three subtasks. The
current parameters for those subtasks are:
Task Start % Compl Actual Dur Duration Pred
A 3/21/06 50 5d 10d
B 4/4/06 30 6d 20d A
C 5/2/06 100 14d 14d B
The summary line for these tasks will then show:
(5+6+14)/(10+20+14) * 100 = 56.8% or 57% as rounded
(Note that the summary completion is independent of task dependencies)
And the progress line for the summary will show progress up through:
3/21/06 + 56.8% * 44 = 4/24/06 (duration is in working days)
Hope this clarifies.
John
Project MVP