R
Rhammia Immanuel
I am using Standalone version of Project 2002 and I use Request progress
information using Email workgroup as we are not using Project server.
My question is how do I protect the Remaining hours field in the email I
send to resources or not even display them. I go into Tools, customize,
published fields and not able to remove the Remaining hours field from the
Task view.
Would appreciate any help that I could get.
Thank you.
Rhammia Immanuel
information using Email workgroup as we are not using Project server.
My question is how do I protect the Remaining hours field in the email I
send to resources or not even display them. I go into Tools, customize,
published fields and not able to remove the Remaining hours field from the
Task view.
Would appreciate any help that I could get.
Thank you.
Rhammia Immanuel