BCWP does not calculate when the task is ahead of schedule. A resource is
assigned. The resource has a dollar value. The baseline has been set. The
percent complete is greater than 0 and less than 100. This is happening
throughout the project schedule. Negative variances are fine.
assigned. The resource has a dollar value. The baseline has been set. The
percent complete is greater than 0 and less than 100. This is happening
throughout the project schedule. Negative variances are fine.