DWilliams
I am having a problem with Project on my my local computer. If I try to
create new project file from my local computer, try to create a new project
file from an existing file, or try to migrate a schedule and apply a
customized calendar (9 hour work days)to it, it will not compute 9 hr days
for a resource. If I take an existing file from our network drive I have no
problems with the calculations. My collegues and I have tried everything we
know to do.
DJW