bcaplan1974
Hi,
New to MS Project and trying to solve a problem that may be common -
I've created a resource that has max units of 50% (their time is split
between two of my projects) I was sure in the past that when I assigned
work to a resource with this setup the task duration for the tasks they
were assigned adjusted for this (ie. I assign them 2 days of work and
with a 50% max unit setting this should take 4 days duration etc.)
This isn't working for me. Anyone have suggestions?
Thanks,
Breton
New to MS Project and trying to solve a problem that may be common -
I've created a resource that has max units of 50% (their time is split
between two of my projects) I was sure in the past that when I assigned
work to a resource with this setup the task duration for the tasks they
were assigned adjusted for this (ie. I assign them 2 days of work and
with a 50% max unit setting this should take 4 days duration etc.)
This isn't working for me. Anyone have suggestions?
Thanks,
Breton