Hi,
I am using Project 98 to cost my resources that charge variable rates
depending on what time they work. Example, normal working day (9-5) is
charged at a normal rate, any time after that is overtime. The first 2
hours of overtime is charged at time and a half and any hours after
that (or weekends) is charged at double time. The problem of-course is
that Project only allows 1 Overtime field. Using an additional Cost
Table doesn't help because they are task specific. Any help please???
Caroline