Project 98 says resource will work 51 hours per day

V

Virginia

I have one resource who works 8 hours a day. I want
Project 98 to spread out the work over a year so that he
can get it done in 8 hours per day. After typing in the
links and tasks, Project 98 gave me a 2-week completion
schedule. The problem with that schedule is that the
resource is working 51 hours per day on some days. I
shoudn't have to create start dates for each tasks so as
to spread them out; I want the computer to do it. Any
ideas? Thank you.
 
M

Mike Glen

Virginia,

Welcome to the Microsoft Project newsgroup :)

Try Tools/Resource Levelling/Level Now.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 