Hello La0d0g,
If you are using Project 2007, you can use the Set Reminder button on
the Tracking toolbar to send the task to the resource's Outlook 2007
task list. You need to have entered the email address for each
resource and assigned the resource. However, there is no link between
the task in Project and the task in Outlook, so if the schedule of the
task changes, you'll need to send a new reminder.
I hope this helps. Let us know how you get along.
Julie
Project MVP