P
Paul
Hi,
Would be grateful for any advice re a project I am about to start planning &
scheduling.
The project is one of those "innovation" type "projects" i.e. where the
objectives are very unclear and what is to be done is unclear (lots of
uncertainty and ambiguity). more a give a few things a go and take it as it
comes type of affair. Also most of the tasks are difficult to define and so
the amount of "Work" isn't what is really driving the schedule (eg We'll be
telling a couple of analysts to work on requirements for a couple of weeks
to see what they can come up with rather than thinking that there is 20 days
of work on requirements so 2 people can do it in 10 elapsed days).
I am also quite keen to "time-box" so want to see what we can do in 2 months
and then take stock.
My approach is to do the following:
Set all the tasks to default to fixed duration and use these fixed durations
to drive the scheduling.. But then I want to fix the end date, define the
project logic (ie dependencies/critical path) and schedule backwards from
the end date.
I hope this would give us a tool where we could play "what-if scenarios" (eg
what if we make the requirements shorter, what if we did a shorter build
phase etc!)
My questions are: 1. Is this a sensible approach for this type of problem,
2. What type of dependencies etc do I need to use to get it to schedule
backwards from an end date (I am used to scheduling forwards!) 3. do I need
to set effort driven = no? and finally are there any other
approaches/suggestions for doing this type of "project" where the "bridge is
being constructed as you walk on it" and where there is little past
experience to base durations and best approach on?
Hope this makes some, grateful for any thoughts.
Thanks
Paul
Would be grateful for any advice re a project I am about to start planning &
scheduling.
The project is one of those "innovation" type "projects" i.e. where the
objectives are very unclear and what is to be done is unclear (lots of
uncertainty and ambiguity). more a give a few things a go and take it as it
comes type of affair. Also most of the tasks are difficult to define and so
the amount of "Work" isn't what is really driving the schedule (eg We'll be
telling a couple of analysts to work on requirements for a couple of weeks
to see what they can come up with rather than thinking that there is 20 days
of work on requirements so 2 people can do it in 10 elapsed days).
I am also quite keen to "time-box" so want to see what we can do in 2 months
and then take stock.
My approach is to do the following:
Set all the tasks to default to fixed duration and use these fixed durations
to drive the scheduling.. But then I want to fix the end date, define the
project logic (ie dependencies/critical path) and schedule backwards from
the end date.
I hope this would give us a tool where we could play "what-if scenarios" (eg
what if we make the requirements shorter, what if we did a shorter build
phase etc!)
My questions are: 1. Is this a sensible approach for this type of problem,
2. What type of dependencies etc do I need to use to get it to schedule
backwards from an end date (I am used to scheduling forwards!) 3. do I need
to set effort driven = no? and finally are there any other
approaches/suggestions for doing this type of "project" where the "bridge is
being constructed as you walk on it" and where there is little past
experience to base durations and best approach on?
Hope this makes some, grateful for any thoughts.
Thanks
Paul