Project duration decimal displayed

L

Lawrence

Input tasks and sub tasks. Found decimal points in the Task Duration where
sub tasks are integer. Dont want decimal, how can I correct it?
 
J

Jan De Messemaeker

Hi,

You probably have a difference between working time and the definition of
what is "a day".
Do rea FAQ 5 - see URL of the faqs in my signature.
HTH
 