D
davies
I'm new to MS Project and I've taken a few classes. I want my tasks to
complete w/in the duration that I gave them. Ex: Design: 9 Days with 2
resource at 100%. What it is doing is taking 1 res = 30/hr and 50/hr =
5760.00 for this task. Acutally what I want it to do is have this task be
completed within the 9 days. They will not be working on this task for 9
days * 8 hours/day. I know I'll have to put in how many hours it actually
took on the resource sheet. Any suggestions? I have an end date that we
have to hit. I dont want my resources leveled or split. The team has many
task to work on in the same time frame. Thanks any suggestions would be
helpful!
complete w/in the duration that I gave them. Ex: Design: 9 Days with 2
resource at 100%. What it is doing is taking 1 res = 30/hr and 50/hr =
5760.00 for this task. Acutally what I want it to do is have this task be
completed within the 9 days. They will not be working on this task for 9
days * 8 hours/day. I know I'll have to put in how many hours it actually
took on the resource sheet. Any suggestions? I have an end date that we
have to hit. I dont want my resources leveled or split. The team has many
task to work on in the same time frame. Thanks any suggestions would be
helpful!