Somehow someone has entered duration in hours in the project plan with which
we're working. Is there anyway to "bulk change" all durations to days?
 
J

John

Rod C said:
Somehow someone has entered duration in hours in the project plan with which
we're working. Is there anyway to "bulk change" all durations to days?

Rod,
Sure, use the Adjust Dates found on the Analysis Toolbar. You might also
want to go to Tools/Options/Schedule tab and insure or change the
"duration is entered in:" selection to "days".

John
Project MVP
 
J

Jan De Messemaeker

Hi all,

Sorry John, it's not the Adjust dates function that does this but the
Format_Duration macro (to be reached through Tools, Macro, Macros).
Hope this helps,
 
J

John

Jan De Messemaeker said:
Hi all,

Sorry John, it's not the Adjust dates function that does this but the
Format_Duration macro (to be reached through Tools, Macro, Macros).
Hope this helps,

Jan,
You are absolutely right. My mind was in a different place and I'm not
sure where. Thanks for submitting the correction.

John
 