Project Information Dialog

K

Karen

When I open the "Project Information" dialog box when I
start a project, the status date is set to NA - why is
that?

Thank you
 
D

Dale Howard [MVP]

Karen --

Generally speaking, the Status Date is ending date of the last reporting
period. So, if I was collecting project progress for last week, the Status
Date would be 3/25/05. The Status Date for this week reporting period is
4/1/05 and for next week it is 4/8/05. Because the Status Date continues to
change over the life of the project, I believe Microsoft sets the default
Status Date value to NA, which forces you to select the correct ending date
for your last reporting period. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top