I have 4 large projects all included in a Master with shared Resource
Pool. To assign priorities does each sub-task in each project have to
be prioritised within the entire master or can I assign a priority to
each project such that Project A is top priority and then assign sub-
tasks relatively within each sub-project.
Let me try an illustrate as I re-read that and confused myself!!
Priority Master Project
900 Project A
700 Task 1
500 Task 2
300 Task 3
700 Project B
700 Task 1
500 Task 2
300 Task 3
500 Project C
700 Task 1
500 Task 2
300 Task 3
So do all Task 1's above carry even weight when being leveled at
Master Project level or does every task in Project A take precedence
over those in B and C due to B and C carrying lower priority in the
whole scheme of things?
Again thanks in advance for any help.
Rgds
Pool. To assign priorities does each sub-task in each project have to
be prioritised within the entire master or can I assign a priority to
each project such that Project A is top priority and then assign sub-
tasks relatively within each sub-project.
Let me try an illustrate as I re-read that and confused myself!!
Priority Master Project
900 Project A
700 Task 1
500 Task 2
300 Task 3
700 Project B
700 Task 1
500 Task 2
300 Task 3
500 Project C
700 Task 1
500 Task 2
300 Task 3
So do all Task 1's above carry even weight when being leveled at
Master Project level or does every task in Project A take precedence
over those in B and C due to B and C carrying lower priority in the
whole scheme of things?
Again thanks in advance for any help.