JoeVolcano
I've been a project user for many years. The current version has become
almost unusable. Creating circular links that cannot be undone. Tasks
that wont level properly. Leveling ignores the priorities and leveling
creates task splits when told not to.
I have the latest update from Microsoft (Maybe that is the problem!)
This has become very frustrating, two of my managers have spent days
working on schedules that should take hours...
ARG!