P
PeteK
Does anyone know how I can setup a project so that a resource could enter
more than 8 hours in a day (basically overtime) and not have Project Server
push the task end date out? I believe I can do this if I increase the
working hours for the resource but then when I look at the resource
availability their capacity level is increased to the amount I set. I want
the resource to have the standard 8 hours a day but allow them to work
additional hours on a task if need be without pushing the task due date. Any
suggestions appreciated.
PeteK
more than 8 hours in a day (basically overtime) and not have Project Server
push the task end date out? I believe I can do this if I increase the
working hours for the resource but then when I look at the resource
availability their capacity level is increased to the amount I set. I want
the resource to have the standard 8 hours a day but allow them to work
additional hours on a task if need be without pushing the task due date. Any
suggestions appreciated.
PeteK