I am using Baseline Cost field in several views and the views show
information on multiple projects with each project taking up one row, along
certain consolidations based on Enterprise outline codes.
When I do rebaseline in some projects, the current baseline values go into
fields such as Baseline Cost 1, Baseline Cost 2 etc. but I have only one
column in my view - Baseline Cost.
The view ends up showing the original baseline for projects where I have
rebaselined.
Is there a field or concept of getting the latest baseline of a project,
something that is definitely bound to vary from one project to another ? but
show that under a column in the view - Baseline cost ?
thanks
Praby Ram
Covansys
information on multiple projects with each project taking up one row, along
certain consolidations based on Enterprise outline codes.
When I do rebaseline in some projects, the current baseline values go into
fields such as Baseline Cost 1, Baseline Cost 2 etc. but I have only one
column in my view - Baseline Cost.
The view ends up showing the original baseline for projects where I have
rebaselined.
Is there a field or concept of getting the latest baseline of a project,
something that is definitely bound to vary from one project to another ? but
show that under a column in the view - Baseline cost ?
thanks
Praby Ram
Covansys