Project Timing

P

Project Server

Problem 1
------------
I have created a calander for my project in which I have specified as 26
working days per month.
I have created few resources in and in their calander, i have coosen the
above calander and in project too, i have used the same calander.
These resources have been assigned as some amount per month. when i try to
determine the project cost, i get the per day cost on only 20 days instead
of 26 days. What may be the problem?

Problem 2
 