Project Update

J

John

I am having issues with resource time being sent to the correct PM. I owned
a project but transferred it to another PM. I asked all resources to send me
their updates and then I processed them. I changed the owner to the new PM
who then opened the project and did a Collaborate/Publish/Republish
Assignments and selected Become the Project Manager for the tasks check box;
however, I am still getting updates from one of the resources. I have
repeated the process to no avail. Any thoughts?
 
K

Karen

If you are only getting updates from one resource, my
guess is all tasks weren't selected when you republished.
Have you tried it again after selecting view all tasks?
 
J

John

Karen,
No, I had the new PM select entire project on more than one occasion, and I
am still getting updates for this one particular resource. What I might try
is to have the new PM just select the ones I am getting and see if that
works. I'll let you know.

Karen said:
If you are only getting updates from one resource, my
guess is all tasks weren't selected when you republished.
Have you tried it again after selecting view all tasks?
 