J
JungleBoy
Hi,
I have created a fe views in the PWA Project center. When I change the views
i.e. remove and add fields to them it can take 2-3 days for the view to get
updated in the project center, until then it shows the old view. Some of the
fields in the view are Enterprise oputline codes using formulae.
I update the OLAP cube as soon as I update the view in the project center
but it still does not update the view for user. Anythins I can do to update
the view for use in PWA.
Thanks
I have created a fe views in the PWA Project center. When I change the views
i.e. remove and add fields to them it can take 2-3 days for the view to get
updated in the project center, until then it shows the old view. Some of the
fields in the view are Enterprise oputline codes using formulae.
I update the OLAP cube as soon as I update the view in the project center
but it still does not update the view for user. Anythins I can do to update
the view for use in PWA.
Thanks