Propsed/Committed

R

Rami

Hello

When you build the team of the project, you can specify is the resource is
committed or propsed.

Now, can I disable this property for the project managers and make all the
resources that they add for the project proposed? I need the resource manager
to be the one who change them later on to committed.

Is it possible?

Thanks
Mo
 
M

Mike Glen

Hi Mo,

This sounds like the pro/server version. Try posting on the server
newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion
products and other useful Project information can be seen at this web
address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP

Hello

When you build the team of the project, you can specify is the
resource is committed or propsed.

Now, can I disable this property for the project managers and make
all the resources that they add for the project proposed? I need the
resource manager to be the one who change them later on to committed.

Is it possible?

Thanks
Mo
Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm
 
D

Dale Howard [MVP]

Mo --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is devoted to
the Microsoft Project desktop application only. To answer your question,
set the Booking value for each resource to Proposed in the Enterprise
Resource Pool. This makes Proposed the default value for every assignment.
Hope this helps.
 