Published assignments icon

J

Jeff

How do I remove the envelope and question mark located in
the Indicators column? This envelope and question mark
have "There has not yet been a response to all the
Published Assignments messages for this new task" note
when the mouse is places over it. I do not have email
addresses attached to any task in this plan.
 
D

Dale Howard

Jeff --

In a project plan in Microsoft Project 2002, when you formally request a
status update on one or more tasks by clicking Collaborate - Request
Progress Information, the following will happen:

1. The resources affected by this request will receive an e-mail to notify
them of your request

2. Microsoft Project 2002 will place an indicator in the Indicators column
showing that you are awaiting a task update (the indicator will be a yellow
envelope with a small clock and a purple question mark symbol below the
envelope)

3. Project Web Access will place a purple question mark indicator in the
Indicators column of the Tasks page for the tasks of each affected resource

What you are asking your resources to do is to immediately report their
progress on each task for which you requested a progress update. What the
resource should do is to immediately enter their actuals for the tasks you
are requesting and during the time period you are requesting, and then to
click either the Update Selected Rows button or the Update All button.

When you receive the appropriate task updates from the affected resources,
you will need to Accept or Reject each update on the Updates page of PWA,
and then click the Update button. Of course, at this point Microsoft
Project 2002 will be launched, the project plan will be opened, and the task
updates will be entered into the project plan.

At this point, those special "awaiting task update" indicators will be
cleared for each task in which EVERY resource assigned has sent a task
update. In fact, the ONLY way to clear this indicator on a task is when
every resource assigned to the task sends an update for that requested task.
Hope this answers your question.
 
J

Jack D.

Jeff said:
How do I remove the envelope and question mark located in
the Indicators column? This envelope and question mark
have "There has not yet been a response to all the
Published Assignments messages for this new task" note
when the mouse is places over it. I do not have email
addresses attached to any task in this plan.

If you manually want to clear the icon you can do this by switching to the
resource usage view.
Insert the column for "response pending", "team status pending" and "update
needed". Each of these clears one of the icons, but I have forgotten which
one goes with each icon. If you insert the column you will find out though.
Just set the field to "No" and the icon will disappear.

At least in Project central these fields had no effect on how the responses
are handled but merely are used to show or hide the indicator. You can clear
them and updates will still proceed in the same way. I expect it is the same
for Project Server.

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP


+++++++++++++++++++
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top