Dear All,

In the Ms. Project, I cannot find values for column PV [Planned Value of
work schedule] and BAC [Budget At completion]. I want to add these two
columns into the cost table but cannot find it in the available list. Please
kindly advise.



Regards,
LG
 
D

Dave

LG said:
Dear All,

In the Ms. Project, I cannot find values for column PV [Planned Value of
work schedule] and BAC [Budget At completion]. I want to add these two
columns into the cost table but cannot find it in the available list. Please
kindly advise.



Regards,
LG

PV is BCWS and BAC is baseline cost
 