Hello everyone!

I just setup a Project Server 2007 for testing, created a project and have
been working with it via the PWA portal just fine. I'm now trying to use the
integration with Outlook 2007 to enter time via the timesheet.

I have installed the outlook add-in from the project server link, I've
synced and added the tasks to outlook.

However, when I open the task, the task does not have any Project
information like the timesheet tab, etc. It's just a generic task type.

What am I missing?
 
J

JulieS

Hello Mike,

As you have not yet received an answer in this newsgroup and your
question concerns Project Server, I suggest you re-post your
question to the project server newsgroup
(microsoft.public.project.server) if you haven't already posted there.

Although most of the folks who answer questions in the newsgroups visit
all the groups, I think there's a higher concentration of "server gurus"
there and you may get a quicker answer.

I hope this helps.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
J

JulieS

Hi Kent,

If Mike did get an answer, it is likely the question was answered in the
Project Server newsgroup where I redirected him.

Try posting the full details of your question to the project server
newsgroup.

I hope this helps.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top