Asif Memon
I want to add task of "pouring concrete" of 100 cubic metre. each cubic meter
requires 400 kg of cement and 1.50 cum aggregate. How can i work out total
resource requirement and assign these resources?
requires 400 kg of cement and 1.50 cum aggregate. How can i work out total
resource requirement and assign these resources?