Simon Shutter
Hi,
If I have a resource that has an average 20% of availability to a project, I
set the max units to 20%. However, if, in a given week the resource works
100% on the project on one day and 0% the rest of the week, he/she is shown
as overallocated.
What is the best way to manage this situation and assign work? I don't want
to update his/her resource calendar and specify different availabilities
based on project demands.
Tx