Question using formula in Project professional

B

Bill

I am using the following formula to get the variance of work to display in
one of our views.

I placed the formula in one of the duration1 field. The formula is

IIf([Actual Work]=0,0,[Actual Work]-[Baseline Work])

Everything works fine except I get the result in days instead of hours.
What do I need to do to get the correct units.

Thanks

Bill
 
D

Dale Howard [MVP]

Bill --

When you placed the formula in a custom Duration field, the result is
formatted in days because the default measure of Duration is days. Instead,
place the formula in a custom Number field, but divide the result by 60, as
Work is stored in minutes in the Project Server database. Hope this helps.
 
M

Mike Glen

Hi Bill,

Try posting on the server newsgroup as this one's closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top