R&D Change Management in MSP

A

Andrew

1) Am working w/ an R&D department to develop standard development project
template
2) Due to nature of product, changes are requested by the end-user
throughout the project.
3) Each change stops work along the previous track, and kicks off a new
track of activities.

I would like to be able to track exactly how much rework is involved due to
the new change, track time against the change, and then also show the impact
to the overall schedule of the change.

This would allow us to collect data for better planning of future projects.
(i.e. "We can anticipate 6-7 changes, w/ each change causing an additional
450 man hours.")

Anyone have any suggestions on how to best represent this change in either a
MPP or MSPS 2003 environment? Since this is a fresh implementation, we have
the chance to get a procedure in place from the beginning.

There is practically nothing that can be done to reduce the number of
changes, so any solution must work within that environment.
 
M

Mike Glen

Hi Andrew,

Welcome to this Microsoft Project newsgroup :)

Well... as a starter, try using an interim baseline at each major change
point. You can then compare baseliness as time goes on.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top