re-priorities existing projects

F

Feeon

In Project 2003 am I able to add new projects or re-prioritise existing
projects in the workstack whilst retaining all associated resourcing actuals
& forecasts.
 
J

Jan De Messemaeker

Hi Feeon,

It would help a great deal should you tell us a bit about the environment
you want to work in.
Are you using Project Server?
If not, do you connect your projects to a common resource pool?
What do you mean by a workstack (this is not a Project leyword so I'm not
sure)

By all means, Priorities do not alter any task in any project as long as you
don't do Resource Leveling.
And leveling will only work on the open project, or on the projects
connected to a common resource pool insofar they are open at the time of
leveling.

Hope this helps
 