When I add recurring meetings, such as 1 hr per week. It shows one hour for
every day of the week for each resource assigned. Does anyone know what is
happening behind the scene?

Thanks
 
J

Jack Dahlgren

Are you assigning the resources to the summary task or the individual meetings?