Recurring Task

L

Ldyflyr

Hi:

How do I create a task that will take 1 hour a day for 2 weeks, Monday to
Friday only?

It is a status meeting that I need to show on the project plan.

Thanks,
 
J

Jim Aksel

Insert/Recurring Task...
However, this hard codes the dates.

If you wish to have them linked, you'll need to enter each one separately
and then link them. You can link the tasks by selecting all of them and then
click on the chain link.

To obtain a correct work/duraion, you need to use "Fixed Duration" and then
assign resources. For example, if 5 people attend your 1 hour meeting this
is a five-man-hour meeting with a fixed duration of 1 hour.
 