S
simon.feirclough
Have a scenario in a closed plan where a number of tasks are not set to
100% complete and have durations that carry them well into the future
eg 2049. Both the duration and date are incorrect.
I assumed one could simply update the duration to bring the dates back
in line and then set to 100% complete.
However, when I reduce the duration so the finish date is in 2006 the
Actual Work falls. The Actual Work Protected remains unchanged.
In short what is the simplest way in MS Project, to update the plan to
get end dates that are no later than 2006, while preserving the "Actual
Work" values ?
Thanks
Simon
100% complete and have durations that carry them well into the future
eg 2049. Both the duration and date are incorrect.
I assumed one could simply update the duration to bring the dates back
in line and then set to 100% complete.
However, when I reduce the duration so the finish date is in 2006 the
Actual Work falls. The Actual Work Protected remains unchanged.
In short what is the simplest way in MS Project, to update the plan to
get end dates that are no later than 2006, while preserving the "Actual
Work" values ?
Thanks
Simon