B
Bill Bradshaw
Resource 1 by itself will take 5 days duration to complete a task. I want to
add Resource 2 which is 150% more productive than Resource 1. This should
reduce the duration to 2 days from 5 days. By increasing Resource 2's units
from 100% to 150% will give me the correct duration of 2 days but it also
gives me an over allocation error (which it should). So how do I handle
resources assigned to a task which are doing the same work but have different
productivity rates?
<Bill>
add Resource 2 which is 150% more productive than Resource 1. This should
reduce the duration to 2 days from 5 days. By increasing Resource 2's units
from 100% to 150% will give me the correct duration of 2 days but it also
gives me an over allocation error (which it should). So how do I handle
resources assigned to a task which are doing the same work but have different
productivity rates?
<Bill>