I am having a problem in Project 2003 with Remaining Work being added back.
As project admin, I generally log onto PWA for any resource that leaves the
project to make sure Remaining Work has been adjusted to zero for all tasks.
In many instances, I am noticing that Project is automatically adding back
Remaining Work for some (but not all) of these resources (at a later time,not
instanteously). Generally, it is an insignificant amount of hours (one hour
here, one there, lots of times a partial hour on an activity). But I want to
close out these resources and have a true reflection of Remaining Work for
the project.
We have SP1 installed.
Any ideas?
As project admin, I generally log onto PWA for any resource that leaves the
project to make sure Remaining Work has been adjusted to zero for all tasks.
In many instances, I am noticing that Project is automatically adding back
Remaining Work for some (but not all) of these resources (at a later time,not
instanteously). Generally, it is an insignificant amount of hours (one hour
here, one there, lots of times a partial hour on an activity). But I want to
close out these resources and have a true reflection of Remaining Work for
the project.
We have SP1 installed.
Any ideas?