A
alex
Hi,
Knowledege:
I use since 2 years the EPM solution
Prerequisites:
I enter the real start date for the work.
And the context is the following:
I initialise a task with fixed duration or fixed capacity or fixed work, the
final behavior is the same.
How to reproduce:
I have a task with an estimate duration, I just know I want to assign some
resource.
I did an estimate about the work.
The mandatory action is the start and finish shouldn't change.
But if you follow the steps below, you realize it's not working.
If you add constraint to finish not later than, it's not change anything.
I have a task begin this monday and finish this friday.
One resource has 16 work planified on the week. The resource records no
hours in the timesheet except the last day: Friday and she records only 8
hours.
In that case the remaining work is 8 hours.
The resource saves and submits the timesheet, import the timesheet in the
task, save and submit.
The project manager accepts the hours and apply to the plan.
In that case, the task where there is still 8 hours in remaining work has
the date changed and the duration.
Why?
Because Microsoft Project determines there is remaing work and decides by
itself to move the remaining work later. MSP see there isn't have more days
available because the task finish this friday. So MSP decided to move
duration and by consequently the finish date.
I takes some captures find in this link
http://docs.google.com/Doc?id=dgq4sw2r_20268v9vddff
It's not the first time this behavior happened.
How can I manage this?
It's like a bug and maybe Microsoft Project is not the good tool to use.
So I'm turn on you because it's around 2 years I work on this product and I
begin to be really desesperate about the unexpected behavior. I defend this
product but it's difficult on this point, it's a blocking point.
So I really appreciate an help.
best regards,
Alexandre BARAULT
Knowledege:
I use since 2 years the EPM solution
Prerequisites:
I enter the real start date for the work.
And the context is the following:
I initialise a task with fixed duration or fixed capacity or fixed work, the
final behavior is the same.
How to reproduce:
I have a task with an estimate duration, I just know I want to assign some
resource.
I did an estimate about the work.
The mandatory action is the start and finish shouldn't change.
But if you follow the steps below, you realize it's not working.
If you add constraint to finish not later than, it's not change anything.
I have a task begin this monday and finish this friday.
One resource has 16 work planified on the week. The resource records no
hours in the timesheet except the last day: Friday and she records only 8
hours.
In that case the remaining work is 8 hours.
The resource saves and submits the timesheet, import the timesheet in the
task, save and submit.
The project manager accepts the hours and apply to the plan.
In that case, the task where there is still 8 hours in remaining work has
the date changed and the duration.
Why?
Because Microsoft Project determines there is remaing work and decides by
itself to move the remaining work later. MSP see there isn't have more days
available because the task finish this friday. So MSP decided to move
duration and by consequently the finish date.
I takes some captures find in this link
http://docs.google.com/Doc?id=dgq4sw2r_20268v9vddff
It's not the first time this behavior happened.
How can I manage this?
It's like a bug and maybe Microsoft Project is not the good tool to use.
So I'm turn on you because it's around 2 years I work on this product and I
begin to be really desesperate about the unexpected behavior. I defend this
product but it's difficult on this point, it's a blocking point.
So I really appreciate an help.
best regards,
Alexandre BARAULT