A
Al
Hi
I use Project 2002.
I have a number of individual MS Project files that represent different
projects we are working on. All of the current projects are linked to
another MS Project file to show a summary of current projects in one view.
The individual project files are linked to the Project Summary by clicking
on "Insert / Project" and then browsing to the file.
The Project Ssummary file has a master list of resources. To make use of
this list, in each of the individual project files I click on "Tools /
Resource Sharing / Share resources". I then click on "use resources / from:
and select the project summary file.
This all works fine so far. However, the project summary is designed to
show current projects only. Therefore, when a project is complete or
cancelled, the tasks for this project are removed via the Gantt chart view
by simply deleting the project heading. When I then look at the Resource
Usage view, the tasks from the deleted project can still be seen against the
appropriate resources. How do I get the task information to disappear from
the resources view as it does from the gantt view?
Any help would be greatly appreciated.
Thanks
Alex
I use Project 2002.
I have a number of individual MS Project files that represent different
projects we are working on. All of the current projects are linked to
another MS Project file to show a summary of current projects in one view.
The individual project files are linked to the Project Summary by clicking
on "Insert / Project" and then browsing to the file.
The Project Ssummary file has a master list of resources. To make use of
this list, in each of the individual project files I click on "Tools /
Resource Sharing / Share resources". I then click on "use resources / from:
and select the project summary file.
This all works fine so far. However, the project summary is designed to
show current projects only. Therefore, when a project is complete or
cancelled, the tasks for this project are removed via the Gantt chart view
by simply deleting the project heading. When I then look at the Resource
Usage view, the tasks from the deleted project can still be seen against the
appropriate resources. How do I get the task information to disappear from
the resources view as it does from the gantt view?
Any help would be greatly appreciated.
Thanks
Alex