Shadowman13 said:
How can I delete or remove a task's constraints? Is this possible? I don't
need to change the task's start date or its duration, so it should be
possible to delete the task's constraint, right?
Shadowman,
There are basically two types of constraints - link based and time
based. Time based constraints can be seen by showing the Constraint Type
field as a column in the view. "No" constraint means the type is,
"as-soon-as-possible". Many new users have a tendency to input Start
and/or Finish dates directly. Doing so creates a "start-no-earlier-than"
or "finish-no-later-than" constraint depending on which was the last
entry. If Start dates for your tasks were manually entered and you then
change the constraint from "start-no-earlier-than" to
"as-soon-as-possible", the task Start will "slam" over to the Project
Start Date (Project/Project Information). That's where the other type of
constraint, link based, plays a part.
The most common link based constraint is a finish-to-start predecessor
that defines the Task Start date based on completion status of a driving
task. This type of constraint is desired and in fact recommended in
order to have a dynamic schedule plan. Removing a predecessor link will
have the same effect as removing a time based constraint as long as the
task has not started. Once a task has non-zero %Complete, neither a time
based or link based constraint has any effect.
Hope this helps.
John
Project MVP